Progress Photos

April 2021 - Remixing in Central Area

April 2021 - Remixing in Central Area

April 2021 - Temporary Gravel Cap Removal in Central Area

April 2021 - Temporary Gravel Cap Removal in Central Area

April 2021 - Final Site Grading

April 2021 - Final Site Grading

April 2021 - Removing Tent Parts

April 2021 - Removing Tent Parts

April 2021 - Removing Tent Parts

April 2021 - Removing Tent Parts

April 2021 - Final Site Grading

April 2021 - Final Site Grading

April 2021 - Load-Out of Central Tent Activated Carbon

April 2021 - Load-Out of Central Tent Activated Carbon

April 2021 - Removing Compressed Gas Cages

April 2021 - Removing Compressed Gas Cages

March 2021 - Final Grading Activities

March 2021 - Final Grading Activities

March 2021 - Equipment Demobilization

March 2021 - Equipment Demobilization

March 2021 - CAT 349 Demobilization

March 2021 - CAT 349 Demobilization

March 2021 - Equipment Demobilization

March 2021 - Equipment Demobilization

March 2021 - Preparing Tent Components for Demobilization

March 2021 - Preparing Tent Components for Demobilization

March 2021 - Central Pier Tent Disassembly

March 2021 - Central Pier Tent Disassembly

March 2021 - Central Pier Tent Disassembly

March 2021 - Central Pier Tent Disassembly

March 2021 - Central Pier Tent Capping

March 2021 - Central Pier Tent Capping

March 2021 - Equipment Staging

March 2021 - Equipment Staging

March 2021 - Disassembling the Batch Plant

March 2021 - Disassembling the Batch Plant

March 2021 - Category 1 Concrete Crushing

March 2021 - Category 1 Concrete Crushing

March 2021 - Category 1 Concrete Sizing and Crushing

March 2021 - Category 1 Concrete Sizing and Crushing

March 2021 - Stockpile Soil Loadout with Posi-Shell Spraying

March 2021 - Stockpile Soil Loadout with Posi-Shell Spraying

March 2021 - Central Tent Soil Stockpile

March 2021 - Central Tent Soil Stockpile

March 2021 - Stockpile Soil Loadout

March 2021 - Stockpile Soil Loadout

March 2021 - Equipment Demobilization

March 2021 - Equipment Demobilization

February 2021 - Soil Stabilization Outside Tents in Southwest Area

February 2021 - Soil Stabilization Outside Tents in Southwest Area

February 2021 - Southwest Tent Loaded for Removal

February 2021 - Southwest Tent Loaded for Removal

February 2021 - Disassembly of the Southwest Tent

February 2021 - Disassembly of the Southwest Tent

February 2021 - Disassembly of the Southwest Tent

February 2021 - Disassembly of the Southwest Tent

February 2021 - Clearing inside the Pier Tent

February 2021 - Clearing inside the Pier Tent

February 2021 - Completed Construction of the Pier Tent (final tent)

February 2021 - Completed Construction of the Pier Tent (final tent)

February 2021 - Assembly of the Pier Tent (final tent)

February 2021 - Assembly of the Pier Tent (final tent)

February 2021 - Demobilization of the Maxim Crane

February 2021 - Demobilization of the Maxim Crane

February 2021 - Vapor Phase Carbon Unit Placement for Pier Tent

February 2021 - Vapor Phase Carbon Unit Placement for Pier Tent

February 2021 - Placement of Pier Tent

February 2021 - Placement of Pier Tent

February 2021 - Disassembly of Southwest Tent

February 2021 - Disassembly of Southwest Tent

February 2021 - Disassembly of Southwest Tent

February 2021 - Disassembly of Southwest Tent

February 2021 - Removal of Spent Vapor-Phase Carbon

February 2021 - Removal of Spent Vapor-Phase Carbon

February 2021 - Northern Pier Tent

February 2021 - Northern Pier Tent

February 2021 - Demobilization of CAT 374 Crane

February 2021 - Demobilization of CAT 374 Crane

February 2021 - Snow Removal in Pier Parking Lot

February 2021 - Snow Removal in Pier Parking Lot

January 2021 - Power Washing in Southwest Tent

January 2021 - Power Washing in Southwest Tent

January 2021 - Managing Soil Stockpile in Southwest Tent

January 2021 - Managing Soil Stockpile in Southwest Tent

January 2021 - Slope Restoration in Northeast Area of the Site

January 2021 - Slope Restoration in Northeast Area of the Site

January 2021 - Fresh Carbon Delivery

January 2021 - Fresh Carbon Delivery

January 2021 - Clearing in Central Non-Tent Area

January 2021 - Clearing in Central Non-Tent Area

January 2021 - Soil Solidification in Central Non-Tent Area

January 2021 - Soil Solidification in Central Non-Tent Area

January 2021 - Clearing in Central Non-Tent Area

January 2021 - Clearing in Central Non-Tent Area

January 2021 - Capping in Northern Pier Tent

January 2021 - Capping in Northern Pier Tent

January 2021 - Inside Northern Pier Tent

January 2021 - Inside Northern Pier Tent

January 2021 - Soil Management In Northern Pier Tent

January 2021 - Soil Management In Northern Pier Tent

January 2021 - Soil Solidification in Southwest Tent

January 2021 - Soil Solidification in Southwest Tent

January 2021 - Debris Management in Southwest Tent

January 2021 - Debris Management in Southwest Tent

January 2021 - Pier Building Sign Relocation

January 2021 - Pier Building Sign Relocation

January 2021 - Asphalt Loadout

January 2021 - Asphalt Loadout

January 2021 - Slope Restoration in Northeast Area of the Site

January 2021 - Slope Restoration in Northeast Area of the Site

January 2021 - Slope Restoration in Northeast Area of the Site

January 2021 - Slope Restoration in Northeast Area of the Site

December 2020 - Soil Solidification Sample Collection in the Northeast Pier Tent

December 2020 - Soil Solidification Sample Collection in the Northeast Pier Tent

December 2020 - Central Pier Parking Lot Preparation

December 2020 - Central Pier Parking Lot Preparation

December 2020 - Central Pier Parking Lot Preparation

December 2020 - Central Pier Parking Lot Preparation

December 2020 - Pre-Clearing and Soil Solidification in the Southwest Tent

December 2020 - Pre-Clearing and Soil Solidification in the Southwest Tent

December 2020 - Pre-Clearing and Soil Solidification in the Southwest Tent

December 2020 - Pre-Clearing and Soil Solidification in the Southwest Tent

December 2020 - Removing Wood Debris from the Southwest Tent

December 2020 - Removing Wood Debris from the Southwest Tent

December 2020 - Clearing in the Southwest Tent

December 2020 - Clearing in the Southwest Tent

December 2020 - Dismantling the Final Segment of the Central Tent

December 2020 - Dismantling the Final Segment of the Central Tent

December 2020 - Deconstructing the Central Tent

December 2020 - Deconstructing the Central Tent

December 2020 - Assembling the Northeast Pier Tent

December 2020 - Assembling the Northeast Pier Tent

December 2020 - Placing the Northeast Pier Tent

December 2020 - Placing the Northeast Pier Tent

December 2020 - Installing Rip-Rap along the Hudson River

December 2020 - Installing Rip-Rap along the Hudson River

December 2020 - Reconstructing the Tent in the Northeast Pier Location

December 2020 - Reconstructing the Tent in the Northeast Pier Location

December 2020 - Relocating the Central Tent to the Northeast Pier Location

December 2020 - Relocating the Central Tent to the Northeast Pier Location

December 2020 - Deconstructing the Central Tent

December 2020 - Deconstructing the Central Tent

December 2020 - Capping in the Central Tent

December 2020 - Capping in the Central Tent

November 2020 - Restoration Along the River in Northeast Area of Site

November 2020 - Restoration Along the River in Northeast Area of Site

November 2020 - Preparing to Install Rip-Rap in Northeast Area of Site

November 2020 - Preparing to Install Rip-Rap in Northeast Area of Site

November 2020 - Installation of Temporary Gravel Cap in Central Tent

November 2020 - Installation of Temporary Gravel Cap in Central Tent

November 2020 - Central Tent

November 2020 - Central Tent

November 2020 - Re-Assembly of Southwest Tent in New Location

November 2020 - Re-Assembly of Southwest Tent in New Location

November 2020 - Moving Southwest Tent to New Location

November 2020 - Moving Southwest Tent to New Location

November 2020 - Deconstruction of Southwest Tent

November 2020 - Deconstruction of Southwest Tent

November 2020 - Capping in Southwest Tent

November 2020 - Capping in Southwest Tent

November 2020 - Cutting and Removing Sheet Along Hudson River

November 2020 - Cutting and Removing Sheet Along Hudson River

November 2020 - Hydroseeding for Grass Cap Across River Road

November 2020 - Hydroseeding for Grass Cap Across River Road

November 2020 - Backfill and Compaction for Lawn Cap Across River Road

November 2020 - Backfill and Compaction for Lawn Cap Across River Road

November 2020 - Preparing for Lawn Cap Across River Road

November 2020 - Preparing for Lawn Cap Across River Road

November 2020 - Loadout of Excess Soil in Central Tent

November 2020 - Loadout of Excess Soil in Central Tent

November 2020 - Soil Solidification and Debris Management in Central Tent

November 2020 - Soil Solidification and Debris Management in Central Tent

November 2020 - Soil Solidification in Southwest Tent

November 2020 - Soil Solidification in Southwest Tent

November 2020 - Soil Solidification and Debris Management in Southwest Tent

November 2020 - Soil Solidification and Debris Management in Southwest Tent

October 2020 - Soil Solidification in Southwest Tent

October 2020 - Soil Solidification in Southwest Tent

October 2020 - Clearing in Southwest Tent

October 2020 - Clearing in Southwest Tent

October 2020 - Wood Debris Stockpile in Southwest Tent

October 2020 - Wood Debris Stockpile in Southwest Tent

October 2020 - Debris Management in Southwest Tent

October 2020 - Debris Management in Southwest Tent

October 2020 - Concrete Sizing and Soil Solidification in Southwest Tent

October 2020 - Concrete Sizing and Soil Solidification in Southwest Tent

October 2020 - Final Soil Cap across River Road

October 2020 - Final Soil Cap across River Road

October 2020 - Final Capping across River Road

October 2020 - Final Capping across River Road

October 2020 - Final Capping across River Road

October 2020 - Final Capping across River Road

October 2020 - Soil Solidification in Central Tent

October 2020 - Soil Solidification in Central Tent

October 2020 - Soil Solidification and Debris Management in Central Tent

October 2020 - Soil Solidification and Debris Management in Central Tent

October 2020 - Debris Management in Central Tent

October 2020 - Debris Management in Central Tent

October 2020 - Excavation across River Road for Final Soil and Grass Cap

October 2020 - Excavation across River Road for Final Soil and Grass Cap

October 2020 - Tent Construction and Non-Tent Soil Solidification

October 2020 - Tent Construction and Non-Tent Soil Solidification

October 2020 - Placing Tent Section in Southwest Area

October 2020 - Placing Tent Section in Southwest Area

October 2020 - Relocating Tent Section from Bulkhead to Southwest Area

October 2020 - Relocating Tent Section from Bulkhead to Southwest Area

October 2020 - Temporary Cap Installation in Non-Tent Area

October 2020 - Temporary Cap Installation in Non-Tent Area

September 2020 - Soil Remediation Outside Tents

September 2020 - Soil Remediation Outside Tents

September 2020 - Bulkhead Tent Temporary Cap Installation

September 2020 - Bulkhead Tent Temporary Cap Installation

September 2020 - Bulkhead Tent Temporary Cap Installation

September 2020 - Bulkhead Tent Temporary Cap Installation

September 2020 - Debris in Bulkhead Tent

September 2020 - Debris in Bulkhead Tent

September 2020 - Relocation of Bulkhead Tent Air Handling Unit

September 2020 - Relocation of Bulkhead Tent Air Handling Unit

September 2020 - Debris Management in Central Tent

September 2020 - Debris Management in Central Tent

September 2020 - “Block 93” Pavement (Across River Road from Main Quanta Site)

September 2020 - “Block 93” Pavement (Across River Road from Main Quanta Site)

September 2020 - Paving “Block 93” (Across River Road from Main Quanta Site)

September 2020 - Paving “Block 93” (Across River Road from Main Quanta Site)

September 2020 - Soil Remediation in Bulkhead Tent

September 2020 - Soil Remediation in Bulkhead Tent

September 2020 - Soil Remediation in Bulkhead Tent

September 2020 - Soil Remediation in Bulkhead Tent

September 2020 - Clearing to Prepare for Soil Remediation in Bulkhead Tent

September 2020 - Clearing to Prepare for Soil Remediation in Bulkhead Tent

September 2020 - Gravel Backfill for Grading on “Block 93” (Across River Road from Quanta Site)

September 2020 - Gravel Backfill for Grading on “Block 93” (Across River Road from Quanta Site)

September 2020 - Excavation and Grading on “Block 93” (Across River Road from Quanta Site)

September 2020 - Excavation and Grading on “Block 93” (Across River Road from Quanta Site)

September 2020 - Concrete Crushing Operation

September 2020 - Concrete Crushing Operation

September 2020 - Concrete Loadout from Central Tent

September 2020 - Concrete Loadout from Central Tent

September 2020 - Concrete Stockpile in Central Tent

September 2020 - Concrete Stockpile in Central Tent

August 2020 - Reassembling the Bulkhead Tent

August 2020 - Reassembling the Bulkhead Tent

August 2020 - Moving Half of the Bulkhead Tent

August 2020 - Moving Half of the Bulkhead Tent

August 2020 - Preparing the New Location for the Bulkhead Tent

August 2020 - Preparing the New Location for the Bulkhead Tent

August 2020 - Capping in the Bulkhead Tent

August 2020 - Capping in the Bulkhead Tent

August 2020 - Capping the Central Non-Tent Area

August 2020 - Capping the Central Non-Tent Area

August 2020 - Non-Tent Soil Solidification in the Central Area

August 2020 - Non-Tent Soil Solidification in the Central Area

August 2020 - Surface Preparation Before Moving the Central Tent

August 2020 - Surface Preparation Before Moving the Central Tent

August 2020 - Capping Inside the Central Tent After Soil Solidification

August 2020 - Capping Inside the Central Tent After Soil Solidification

August 2020 - Non-Tent Soil Solidification

August 2020 - Non-Tent Soil Solidification

August 2020 - Clearing for Non-Tent Soil Solidification

August 2020 - Clearing for Non-Tent Soil Solidification

August 2020 - Removing Excess Soil from the Central Tent in Lined Trucks

August 2020 - Removing Excess Soil from the Central Tent in Lined Trucks

August 2020 - Truck Lining Station for Offside Disposal

August 2020 - Truck Lining Station for Offside Disposal

August 2020 - Soil Solidification Inside the Bulkhead Tent

August 2020 - Soil Solidification Inside the Bulkhead Tent

August 2020 - Stockpiles from Building Demolition Debris

August 2020 - Stockpiles from Building Demolition Debris

August 2020 - Applying Posi-Shell to Concrete Stockpile to Control Odors

August 2020 - Applying Posi-Shell to Concrete Stockpile to Control Odors

August 2020 - Developing New River Road Curb Cut

August 2020 - Developing New River Road Curb Cut

July 2020 - Grading Gravel Cap Inside Bulkhead Tent

July 2020 - Grading Gravel Cap Inside Bulkhead Tent

July 2020 - Concrete Processing Area

July 2020 - Concrete Processing Area

July 2020 - Both Halves of Bulkhead Tent Placed in New Location

July 2020 - Both Halves of Bulkhead Tent Placed in New Location

July 2020 - Moving Northern Half of Bulkhead Tent

July 2020 - Moving Northern Half of Bulkhead Tent

July 2020 - Concrete Crushing

July 2020 - Concrete Crushing

July 2020 - Removing Wood Debris in Central Tent

July 2020 - Removing Wood Debris in Central Tent

July 2020 - Clearing Debris in Central Tent

July 2020 - Clearing Debris in Central Tent

July 2020 - Soil Solidification in Central Tent

July 2020 - Soil Solidification in Central Tent

July 2020 - Soil Stabilization in the Central Tent

July 2020 - Soil Stabilization in the Central Tent

July 2020 - Covering the Soil Stockpile

July 2020 - Covering the Soil Stockpile

July 2020 - Debris Management in the Central Tent

July 2020 - Debris Management in the Central Tent

July 2020 - Concrete Stockpile from the Former 115 River Road Building in the Central Tent

July 2020 - Concrete Stockpile from the Former 115 River Road Building in the Central Tent

July 2020 - Clearing the Foundation of the Former 115 River Road Building inside the Central Tent

July 2020 - Clearing the Foundation of the Former 115 River Road Building inside the Central Tent

July 2020 - Managing and Moving Roll-off Containers

July 2020 - Managing and Moving Roll-off Containers

July 2020 - Capping in the Bulkhead Tent

July 2020 - Capping in the Bulkhead Tent

July 2020 - Soil Stabilization in the Bulkhead Tent

July 2020 - Soil Stabilization in the Bulkhead Tent

June 2020 - Central Tent with Sign for Pier Building

June 2020 - Central Tent with Sign for Pier Building

June 2020 - Completed Bulkhead Concrete Cap in the Pier Building Driveway

June 2020 - Completed Bulkhead Concrete Cap in the Pier Building Driveway

June 2020 - Mulch Installation Along the Pier Building

June 2020 - Mulch Installation Along the Pier Building

June 2020 - Pier Building Parking Lot after Repaving

June 2020 - Pier Building Parking Lot after Repaving

June 2020 - Work Area Sweeping After Paving and Striping Outside Pier Building

June 2020 - Work Area Sweeping After Paving and Striping Outside Pier Building

June 2020 - Site Dust Control

June 2020 - Site Dust Control

June 2020 - Soil Stabilization in the Bulkhead Tent

June 2020 - Soil Stabilization in the Bulkhead Tent

June 2020 - Absorbent Boom Swap-Out

June 2020 - Absorbent Boom Swap-Out

June 2020 - Pouring Concrete for Pier Building Office Stairs

June 2020 - Pouring Concrete for Pier Building Office Stairs

June 2020 - Posi-Shell Application at Concrete Stockpile

June 2020 - Posi-Shell Application at Concrete Stockpile

June 2020 - Mulch Installation Along the River

June 2020 - Mulch Installation Along the River

June 2020 - Soil Stockpile Load-Out

June 2020 - Soil Stockpile Load-Out

May 2020 - Load-out of Soil Overburden for Offsite Transport

May 2020 - Load-out of Soil Overburden for Offsite Transport

May 2020 - Concrete Cap Preparation

May 2020 - Concrete Cap Preparation

May 2020 - Grading in the Bulkhead Tent

May 2020 - Grading in the Bulkhead Tent

May 2020 - Concrete Cap Preparation

May 2020 - Concrete Cap Preparation

May 2020 - Restoration of the Slope Along the Northern Fenceline

May 2020 - Restoration of the Slope Along the Northern Fenceline

May 2020 - Assembly of the Central Tent at the Site of the Former 115 River Road Building

May 2020 - Assembly of the Central Tent at the Site of the Former 115 River Road Building

May 2020 - Temporary Cap Installation in the Northwest Tent

May 2020 - Temporary Cap Installation in the Northwest Tent

May 2020 - Assembly of the Central Tent at the Site of the Former 115 River Road Building

May 2020 - Assembly of the Central Tent at the Site of the Former 115 River Road Building

May 2020 - Soil Solidification in Northwest Tent

May 2020 - Soil Solidification in Northwest Tent

May 2020 - Restoration of the Slope Along the Northern Fenceline

May 2020 - Restoration of the Slope Along the Northern Fenceline

May 2020 - Assembly of Central Tent at Site of Former 115 River Road Building

May 2020 - Assembly of Central Tent at Site of Former 115 River Road Building

May 2020 - Loading Demolition Debris for Offsite Transport

May 2020 - Loading Demolition Debris for Offsite Transport

May 2020 - Absorbent Boom Replacement on South Side of Pier Building

May 2020 - Absorbent Boom Replacement on South Side of Pier Building

May 2020 - Pre-Clearing for Soil Treatment Near Pier Building

May 2020 - Pre-Clearing for Soil Treatment Near Pier Building

May 2020 - Overburden Management in Non-Tent Area Near Pier Building

May 2020 - Overburden Management in Non-Tent Area Near Pier Building

May 2020 - Re-Covering Soil Stockpile

May 2020 - Re-Covering Soil Stockpile

April 2020 - iPark Sidewalk Restoration

April 2020 - iPark Sidewalk Restoration

April 2020 - Backfilling in Non-Tent Area

April 2020 - Backfilling in Non-Tent Area

April 2020 - Soil Solidification and Posi-Shell Application in Non-Tent Area Near Pier Building

April 2020 - Soil Solidification and Posi-Shell Application in Non-Tent Area Near Pier Building

April 2020 - Asphalt Removal and Posi-Shell Application in Non-Tent Area Near Pier Building

April 2020 - Asphalt Removal and Posi-Shell Application in Non-Tent Area Near Pier Building

April 2020 - Pre-Clearing for Soil Solidification and Posi-Shell Application in Non-Tent Area Near Pier Building

April 2020 - Pre-Clearing for Soil Solidification and Posi-Shell Application in Non-Tent Area Near Pier Building

April 2020 - Backfilling Over New Stormwater Piping

April 2020 - Backfilling Over New Stormwater Piping

April 2020 - Stormwater Pipe Installation

April 2020 - Stormwater Pipe Installation

April 2020 - Soil Stockpile Load-Out and Posi-Shell Application

April 2020 - Soil Stockpile Load-Out and Posi-Shell Application

April 2020 - Soil Remediation in Non-Tent Area North of the Pier Building

April 2020 - Soil Remediation in Non-Tent Area North of the Pier Building

April 2020 - Load-out of Excess Soil in Stockpile Using Posi-Shell to Minimize Vapors

April 2020 - Load-out of Excess Soil in Stockpile Using Posi-Shell to Minimize Vapors

April 2020 - Relocation of Second Section of Northwest Tent

April 2020 - Relocation of Second Section of Northwest Tent

April 2020 - Relocation of First Section of Northwest Tent

April 2020 - Relocation of First Section of Northwest Tent

April 2020 - Re-Assembling the Bulkhead Tent after Being Moved

April 2020 - Re-Assembling the Bulkhead Tent after Being Moved

April 2020 - River Walk Restoration South of the Pier Building

April 2020 - River Walk Restoration South of the Pier Building

April 2020 - River Walk Restoration South of the Pier Building

April 2020 - River Walk Restoration South of the Pier Building

April 2020 - Temporary Cap Installation in Northwest Tent

April 2020 - Temporary Cap Installation in Northwest Tent

March 2020 - Disassembly of the Bulkhead Tent

March 2020 - Disassembly of the Bulkhead Tent

March 2020 - Overburden Load-Out from the Northwest Tent

March 2020 - Overburden Load-Out from the Northwest Tent

March 2020 - Management of Residual Overburden in the Northwest Tent

March 2020 - Management of Residual Overburden in the Northwest Tent

March 2020 - Soil Stockpile Management with Use of Posi-Shell to Control Odors

March 2020 - Soil Stockpile Management with Use of Posi-Shell to Control Odors

March 2020 - Temporary Cap Installation in Non-Tent Area

March 2020 - Temporary Cap Installation in Non-Tent Area

March 2020 - Temporary Cap Installation in Bulkhead Tent

March 2020 - Temporary Cap Installation in Bulkhead Tent

March 2020 - Absorbent Boom Replacement in Hudson River

March 2020 - Absorbent Boom Replacement in Hudson River

March 2020 - Soil Solidification in the Northwest Tent

March 2020 - Soil Solidification in the Northwest Tent

March 2020 - ISS in a Tent

March 2020 - ISS in a Tent

March 2020 - Soil Stockpile Load-Out into Lined Trucks

March 2020 - Soil Stockpile Load-Out into Lined Trucks

March 2020 - South Parking Lot Paving

March 2020 - South Parking Lot Paving

March 2020 - Pulverizing Concrete

March 2020 - Pulverizing Concrete

March 2020 - Soil Stockpile Management with Odor Control

March 2020 - Soil Stockpile Management with Odor Control

March 2020 - Non-Tent Area ISS and Odor Control

March 2020 - Non-Tent Area ISS and Odor Control

March 2020 - Non-Tent Area ISS and Odor Control

March 2020 - Non-Tent Area ISS and Odor Control

March 2020 - Non-Tent Area ISS Along the Fenceline

March 2020 - Non-Tent Area ISS Along the Fenceline

February 2020 - Soil Stockpile Management with Odor Control

February 2020 - Soil Stockpile Management with Odor Control

February 2020 - ISS in an Un-tented Area along the Fenceline

February 2020 - ISS in an Un-tented Area along the Fenceline

February 2020 - ISS Sample Collection

February 2020 - ISS Sample Collection

February 2020 - Pre-Clearing for ISS

February 2020 - Pre-Clearing for ISS

February 2020 - Gravel Cover Removal and Final Commissioning of a Tent

February 2020 - Gravel Cover Removal and Final Commissioning of a Tent

February 2020 - Tent Assembly

February 2020 - Tent Assembly

February 2020 - Tent Assembly

February 2020 - Tent Assembly

February 2020 - Tent Relocation

February 2020 - Tent Relocation

February 2020 - Relocating a Carbon Air Treatment Unit

February 2020 - Relocating a Carbon Air Treatment Unit

February 2020 - Relocating a Tent

February 2020 - Relocating a Tent

February 2020 - Removing Excess Soil for Offsite Disposal

February 2020 - Removing Excess Soil for Offsite Disposal

February 2020 - Temporary Cap Installation

February 2020 - Temporary Cap Installation

February 2020 - Soil Solidification and Soil Management in the Bulkhead Tent

February 2020 - Soil Solidification and Soil Management in the Bulkhead Tent

February 2020 - End of Day Clean-Up and Posi-Shell Application

February 2020 - End of Day Clean-Up and Posi-Shell Application

February 2020 - Soil Solidification in Front of the Pier Building

February 2020 - Soil Solidification in Front of the Pier Building

February 2020 - Managing Concrete Debris from Clearing for Soil Solidification

February 2020 - Managing Concrete Debris from Clearing for Soil Solidification

January 2020 - Offloading Overburden Soil at Stockpile

January 2020 - Offloading Overburden Soil at Stockpile

January 2020 - Soil Stockpile Management

January 2020 - Soil Stockpile Management

January 2020 - Tent Assembly

January 2020 - Tent Assembly

January 2020 - Site-Wide Posi-Shell Application

January 2020 - Site-Wide Posi-Shell Application

January 2020 - Soil Solidification Inside Bulkhead Tent

January 2020 - Soil Solidification Inside Bulkhead Tent

January 2020 - Soil Solidification in Front of Pier Building

January 2020 - Soil Solidification in Front of Pier Building

January 2020 - Soil Solidification in Front of Pier Building

January 2020 - Soil Solidification in Front of Pier Building

January 2020 - Preparing Area for Soil Solidification

January 2020 - Preparing Area for Soil Solidification

January 2020 - Main Quanta Site Road Maintenance

January 2020 - Main Quanta Site Road Maintenance

January 2020 - Spent Carbon Management

January 2020 - Spent Carbon Management

January 2020 - Soil Stockpile Management with Posi-Shell Application

January 2020 - Soil Stockpile Management with Posi-Shell Application

January 2020 - Assembling Bulkhead Tent in New Location

January 2020 - Assembling Bulkhead Tent in New Location

January 2020 - Relocation of Bulkhead Tent

January 2020 - Relocation of Bulkhead Tent

January 2020 - Lining Truck for Soil Loadout

January 2020 - Lining Truck for Soil Loadout

December 2019 - Leveling Gravel Surface to Prepare for Bulkhead Tent Placement

December 2019 - Leveling Gravel Surface to Prepare for Bulkhead Tent Placement

December 2019 - Reshaping Soil Stockpile to Prepare for Truck Loadout

December 2019 - Reshaping Soil Stockpile to Prepare for Truck Loadout

December 2019 - Conduit Installation for Pier Building Telecommunication Relocation

December 2019 - Conduit Installation for Pier Building Telecommunication Relocation

December 2019 - Temporary Cap Installation in Bulkhead Tent

December 2019 - Temporary Cap Installation in Bulkhead Tent

December 2019 - Pre-Clearing for Soil Remediation in Northwest Tent

December 2019 - Pre-Clearing for Soil Remediation in Northwest Tent

December 2019 - Managing Gravel Cap Along the River

December 2019 - Managing Gravel Cap Along the River

December 2019 - Mobilizing Lift for Moving Bulkhead Tent

December 2019 - Mobilizing Lift for Moving Bulkhead Tent

December 2019 - Completed Installation of Sheets, Whalers, and Tie Rods in Bulkhead Tent

December 2019 - Completed Installation of Sheets, Whalers, and Tie Rods in Bulkhead Tent

December 2019 - Restoration of Privacy Fencing South of Pier Building

December 2019 - Restoration of Privacy Fencing South of Pier Building

December 2019 - Scraping Surface of Soil Solidification to Remove Debris and Loose Material Before Capping in Bulkhead Tent

December 2019 - Scraping Surface of Soil Solidification to Remove Debris and Loose Material Before Capping in Bulkhead Tent

December 2019 - Dump trucks with Liner

December 2019 - Dump trucks with Liner

December 2019 - Paving Operation Completed in South Parking Lot

December 2019 - Paving Operation Completed in South Parking Lot

December 2019 - Applying Asphalt to Utility Trenches and Large Potholes

December 2019 - Applying Asphalt to Utility Trenches and Large Potholes

November 2019 - Absorbent Boom Replacement in Waterway

November 2019 - Absorbent Boom Replacement in Waterway

November 2019 - End of Day Odor Control Activities

November 2019 - End of Day Odor Control Activities

November 2019 - ISS Outside Tents along Bulkhead

November 2019 - ISS Outside Tents along Bulkhead

November 2019 - Clearing and Debris Management

November 2019 - Clearing and Debris Management

November 2019 - Reshaping Soil Stockpile

November 2019 - Reshaping Soil Stockpile

November 2019 - Restoration South of Pier Building

November 2019 - Restoration South of Pier Building

November 2019 - Collecting ISS Compliance Sample

November 2019 - Collecting ISS Compliance Sample

November 2019 - NOdor Control and Clearing

November 2019 - NOdor Control and Clearing

November 2019 - Odor Control and Clearing

November 2019 - Odor Control and Clearing

November 2019 - Removing Concrete Debris

November 2019 - Removing Concrete Debris

November 2019 - Electrical conduit installation in South Parking Lot

November 2019 - Electrical conduit installation in South Parking Lot

November 2019 - ISS within Bulkhead Tent

November 2019 - ISS within Bulkhead Tent

October 2019 - Covered Soil Stockpile at Close of Day

October 2019 - Covered Soil Stockpile at Close of Day

October 2019 - Crane Mobilized for Driving Sheet Piles

October 2019 - Crane Mobilized for Driving Sheet Piles

October 2019 - Pre-clearing Debris in Bulkhead Tent in Preparation for Soil Solidification

October 2019 - Pre-clearing Debris in Bulkhead Tent in Preparation for Soil Solidification

October 2019 - Soil Solidification within Tent in Northwest Area

October 2019 - Soil Solidification within Tent in Northwest Area

October 2019 - Routine Boom Replacement in River

October 2019 - Routine Boom Replacement in River

October 2019 - Lined truck Leaving Station

October 2019 - Lined truck Leaving Station

October 2019 - Pumping Water to Stormwater Treatment System After Rain

October 2019 - Pumping Water to Stormwater Treatment System After Rain

October 2019 - Trucks Removing Soil Offsite Lined with Burrito Bag

October 2019 - Trucks Removing Soil Offsite Lined with Burrito Bag

October 2019 - First day of Offsite Soil Removal in Bulkhead Tent

October 2019 - First day of Offsite Soil Removal in Bulkhead Tent

October 2019 - Outdoor ISS South of Pier Building

October 2019 - Outdoor ISS South of Pier Building

October 2019 - Pre-clearing South of Pier Building to Remove Concrete, Pilings, and Other Debris

October 2019 - Pre-clearing South of Pier Building to Remove Concrete, Pilings, and Other Debris

October 2019 - Repairing Hard Boom South of Pier Building

October 2019 - Repairing Hard Boom South of Pier Building

October 2019 - Moving Stockpiled Soils Within Tent in  Northwest Corner

October 2019 - Moving Stockpiled Soils Within Tent in Northwest Corner

October 2019 - Preparing to Lay Plastic Over Completed ISS and Move Soil Stockpile Within Tent in Northwest Corner

October 2019 - Preparing to Lay Plastic Over Completed ISS and Move Soil Stockpile Within Tent in Northwest Corner

October 2019 - ISS Within Tent in Northwest Corner

October 2019 - ISS Within Tent in Northwest Corner

October 2019 - Routine Soft Boom Changeout

October 2019 - Routine Soft Boom Changeout

October 2019 - Moving Excavator from South of Pier Building to Bulkhead Tent

October 2019 - Moving Excavator from South of Pier Building to Bulkhead Tent

September 2019 - Applying Gravel Cap Over Completed ISS Area South of Pier Building

September 2019 - Applying Gravel Cap Over Completed ISS Area South of Pier Building

September 2019 - Completed Areas South of Pier Building Covered with Temporary Cap After Agency Inspection

September 2019 - Completed Areas South of Pier Building Covered with Temporary Cap After Agency Inspection

September 2019 - Soil Mixing Outside Tent South of Pier Building

September 2019 - Soil Mixing Outside Tent South of Pier Building

September 2019 - Soil Mixing Outside Tent South of Pier Building

September 2019 - Soil Mixing Outside Tent South of Pier Building

September 2019 - Re-shaping Soil Stockpile; Applying Posi-shell Odor Control When Disturbing Soils

September 2019 - Re-shaping Soil Stockpile; Applying Posi-shell Odor Control When Disturbing Soils

September 2019 - Preparing for Cold Weather by Installing “Hot House” over Quanta Main Site Water Meters

September 2019 - Preparing for Cold Weather by Installing “Hot House” over Quanta Main Site Water Meters

September 2019 - Soil Mixing Outside Tent South of Pier Building

September 2019 - Soil Mixing Outside Tent South of Pier Building

September 2019 - Applying Piian Odor Suppressant During Outside Soil Mixing South of Pier Building

September 2019 - Applying Piian Odor Suppressant During Outside Soil Mixing South of Pier Building

September 2019 - Regularly-scheduled Boom Change in River

September 2019 - Regularly-scheduled Boom Change in River

September 2019 - ISS South of Pier Building, Working Outside Tents

September 2019 - ISS South of Pier Building, Working Outside Tents

September 2019 - ISS Cell South of Pier Building, Working Outside Tents

September 2019 - ISS Cell South of Pier Building, Working Outside Tents

September 2019 - New Pier 115 Pedestrian Walkway Completed

September 2019 - New Pier 115 Pedestrian Walkway Completed

September 2019 - Painting New Pier 115 Pedestrian Walkway Railing to Match Original

September 2019 - Painting New Pier 115 Pedestrian Walkway Railing to Match Original

September 2019 - Reshaping Stockpile inside Tent

September 2019 - Reshaping Stockpile inside Tent

September 2019 - Tent Commissioning and Thinning Gravel Cap

September 2019 - Tent Commissioning and Thinning Gravel Cap

September 2019 - Collecting ISS Sample

September 2019 - Collecting ISS Sample

August 2019 - Vapor Sealing Tent (Geotextile and Gravel)

August 2019 - Vapor Sealing Tent (Geotextile and Gravel)

August 2019 - Pre-clearing Before ISS

August 2019 - Pre-clearing Before ISS

August 2019 - Installing Fabric Joints to Connect Three Tent Sections

August 2019 - Installing Fabric Joints to Connect Three Tent Sections

August 2019 - Pumping Stormwater to Treatment System After Heavy Rain and Repairing the Roll-up Door

August 2019 - Pumping Stormwater to Treatment System After Heavy Rain and Repairing the Roll-up Door

August 2019 - Rigging to Perform Pullout Test of Baseplate

August 2019 - Rigging to Perform Pullout Test of Baseplate

August 2019 - Lifting 3rd Section of Tent into Place

August 2019 - Lifting 3rd Section of Tent into Place

August 2019 - Replacing Privacy Screening on Fence

August 2019 - Replacing Privacy Screening on Fence

August 2019 - Installing Fabric on Tent Frame

August 2019 - Installing Fabric on Tent Frame

August 2019 - Assembly of Tent's Center Section

August 2019 - Assembly of Tent's Center Section

August 2019 - Tent's North Section Moved into Position

August 2019 - Tent's North Section Moved into Position

August 2019 - Installing Lift Kit Compression Bars

August 2019 - Installing Lift Kit Compression Bars

July 2019 - Pre-Clearing ISS Cell

July 2019 - Pre-Clearing ISS Cell

July 2019 - Odor and Dust Control for Slope Disturbance in Preparation for Tent Move

July 2019 - Odor and Dust Control for Slope Disturbance in Preparation for Tent Move

July 2019 - Clearing and Debris Management

July 2019 - Clearing and Debris Management

July 2019 - ISS in near Bulkhead

July 2019 - ISS in near Bulkhead

July 2019 - Installing North Blower Piping on Tent near Bulkhead

July 2019 - Installing North Blower Piping on Tent near Bulkhead

July 2019 - Levelling the South Side

July 2019 - Levelling the South Side

July 2019 - Asphalt Load-Out

July 2019 - Asphalt Load-Out

July 2019 - Soil Consolidation

July 2019 - Soil Consolidation

July 2019 - Clearing Obstructions from ISS Cells

July 2019 - Clearing Obstructions from ISS Cells

July 2019 - Absorbent Boom Swap-Out in Waterway

July 2019 - Absorbent Boom Swap-Out in Waterway

July 2019 - Installing Ceiling Fans

July 2019 - Installing Ceiling Fans

July 2019 - North Parking Lot Paving and Sweeping

July 2019 - North Parking Lot Paving and Sweeping

July 2019 - Installing North Roll-Up Door

July 2019 - Installing North Roll-Up Door

June 2019 - Crushing Concrete

June 2019 - Crushing Concrete

June 2019 - Assembling Tent (near river)

June 2019 - Assembling Tent (near river)

June 2019 - Assembling Tent (near river)

June 2019 - Assembling Tent (near river)

June 2019 - Removing Obstructions from Soil Remediation Cells in (northwest corner of Quanta site)

June 2019 - Removing Obstructions from Soil Remediation Cells in (northwest corner of Quanta site)

June 2019 - Soil Remediation in Tent (northwest corner of Quanta site)

June 2019 - Soil Remediation in Tent (northwest corner of Quanta site)

June 2019 - Preparing to Place Tent on Bulkhead

June 2019 - Preparing to Place Tent on Bulkhead

June 2019 - LiftinTent onto Bulkhead

June 2019 - LiftinTent onto Bulkhead

June 2019 - Transporting Stockpile into Tent (northwest corner of Quanta site)

June 2019 - Transporting Stockpile into Tent (northwest corner of Quanta site)

May 2019 - Erecting Area 3A Tent

May 2019 - Erecting Area 3A Tent

May 2019 - Trenching for Pier Building Gas Line Relocation

May 2019 - Trenching for Pier Building Gas Line Relocation

April 2019 - Erecting Area 3A Tent

April 2019 - Erecting Area 3A Tent

April 2019 - Laying Out Area 3A Tent

April 2019 - Laying Out Area 3A Tent

April 2019 - Bulkhead Brackets for Tent Support

April 2019 - Bulkhead Brackets for Tent Support

April 2019 - Tent Support Bracket Installation on Bulkhead

April 2019 - Tent Support Bracket Installation on Bulkhead

April 2019 - Assembling Crane

April 2019 - Assembling Crane

April 2019 - Offloading ISS Tent Delivery

April 2019 - Offloading ISS Tent Delivery

April 2019 - Dust Control Activities

April 2019 - Dust Control Activities

April 2019 - Area 7 Soil Stockpile Posi-Shell Application

April 2019 - Area 7 Soil Stockpile Posi-Shell Application

April 2019 - Grading Area 7 to Prepare for Tent Installation

April 2019 - Grading Area 7 to Prepare for Tent Installation

April 2019 - ISS Tent Generator Gas Line Installation

April 2019 - ISS Tent Generator Gas Line Installation

April 2019 - Erecting Grout Plant Silos

April 2019 - Erecting Grout Plant Silos

April 2019 - Offloading ISS Tent Air Handling Systems

April 2019 - Offloading ISS Tent Air Handling Systems

April 2019 - Grout Plant Water Line Installation

April 2019 - Grout Plant Water Line Installation

April 2019 - Installing ISS Tent Generator

April 2019 - Installing ISS Tent Generator

March 2019 - Demolition Material Management

March 2019 - Demolition Material Management

March 2019 - Compacting Ground Surface in Demo Area

March 2019 - Compacting Ground Surface in Demo Area

March 2019 - Area 3A Soil Stockpile Maintenance

March 2019 - Area 3A Soil Stockpile Maintenance

March 2019 - Demolition Material Management

March 2019 - Demolition Material Management

March 2019 - Trenching for ISS Tent Generator Gas Line and Electric

March 2019 - Trenching for ISS Tent Generator Gas Line and Electric

March 2019 - Preparing Transformer Pad for ISS Tent Electric

March 2019 - Preparing Transformer Pad for ISS Tent Electric

March 2019 - Swapping Absorbent Boom in Waterway

March 2019 - Swapping Absorbent Boom in Waterway

March 2019 - Hammering Above-Grade Building Foundation

March 2019 - Hammering Above-Grade Building Foundation

February 2019 - Segment A Bulkhead Installation

February 2019 - Segment A Bulkhead Installation

February 2019 - Segregating and Stockpiling Demolition Debris

February 2019 - Segregating and Stockpiling Demolition Debris

February 2019 - Sizing Steel for Offsite Disposal

February 2019 - Sizing Steel for Offsite Disposal

February 2019 - Loading Demolition Debris into Roll-Offs

February 2019 - Loading Demolition Debris into Roll-Offs

February 2019 - Segregating and Stockpiling Demolition Debris

February 2019 - Segregating and Stockpiling Demolition Debris

February 2019 - Backfilling Segment B Bulkhead

February 2019 - Backfilling Segment B Bulkhead

February 2019 - Cutting Segment B Sheets to Elevation

February 2019 - Cutting Segment B Sheets to Elevation

February 2019 - Pre-Trenching for Utilities for Bulkhead Installation

February 2019 - Pre-Trenching for Utilities for Bulkhead Installation

January 2019 - 115 River Road Demolition

January 2019 - 115 River Road Demolition

January 2019 - Re-Installing Pier Building Pedestrian Walkway

January 2019 - Re-Installing Pier Building Pedestrian Walkway

January 2019 - Segment A Bulkhead Installation

January 2019 - Segment A Bulkhead Installation

January 2019 - Securing Pier Building Driveway Road Plates in Place

January 2019 - Securing Pier Building Driveway Road Plates in Place

January 2019 - Swapping Absorbent Boom in Waterway

January 2019 - Swapping Absorbent Boom in Waterway

January 2019 - Auxiliary Parking Lot Parking Space Striping

January 2019 - Auxiliary Parking Lot Parking Space Striping

January 2019 - Demolition Material Management

January 2019 - Demolition Material Management

January 2019 - 115 River Road Demolition

January 2019 - 115 River Road Demolition

December 2018 - Preparing Auxiliary Parking Lot Area for Paving

December 2018 - Preparing Auxiliary Parking Lot Area for Paving

December 2018 - Above-Grade Building Foundation Removal

December 2018 - Above-Grade Building Foundation Removal

December 2018 - Demolition Material Management

December 2018 - Demolition Material Management

November 2018 - 115 River Road Exterior Demolition

November 2018 - 115 River Road Exterior Demolition

November 2018 - 115 River Road Exterior Demolition and Dust Control

November 2018 - 115 River Road Exterior Demolition and Dust Control

October 2018 - 115 River Road Interior Demolition

October 2018 - 115 River Road Interior Demolition

November 2018 - 115 River Road Interior Demolition

November 2018 - 115 River Road Interior Demolition

November 2018 - Demolition Debris Management

November 2018 - Demolition Debris Management

October 2018 - 115 River Road Exterior Demolition and Dust Control

October 2018 - 115 River Road Exterior Demolition and Dust Control

October 2018 - 115 River Road Demolition Material Management

October 2018 - 115 River Road Demolition Material Management

October 2018 - 115 River Road Interior Demolition

October 2018 - 115 River Road Interior Demolition

October 2018 - 115 River Road Exterior Demolition and Dust Control

October 2018 - 115 River Road Exterior Demolition and Dust Control

October 2018 - 115 River Road Interior Demolition

October 2018 - 115 River Road Interior Demolition

October 2018 - 115 River Road Exterior Demolition and Dust Control

October 2018 - 115 River Road Exterior Demolition and Dust Control

October 2018 - 115 River Road Interior Demolition

October 2018 - 115 River Road Interior Demolition

September 2018 - 115 River Road Gas and Electric Meter Removal

September 2018 - 115 River Road Gas and Electric Meter Removal

August 2018 - Demobilizing Loader from Main Quanta Site

August 2018 - Demobilizing Loader from Main Quanta Site

August 2018 - Area 7 Soil Stockpile Cover Maintenance

August 2018 - Area 7 Soil Stockpile Cover Maintenance

August 2018 - 115 River Road Clean-Up for Prepare for Demolition

August 2018 - 115 River Road Clean-Up for Prepare for Demolition

August 2018 - Preparing for ACM Abatement at 115 River Road

August 2018 - Preparing for ACM Abatement at 115 River Road

August 2018 - Parking Lot Striping at Area 2

August 2018 - Parking Lot Striping at Area 2

August 2018 - Universal Waste Removal in 115 River Road

August 2018 - Universal Waste Removal in 115 River Road

August 2018 - Deploying Rodent Traps for 115 RR Demolition

August 2018 - Deploying Rodent Traps for 115 RR Demolition

August 2018 - Area 2 Final Capping Activities

August 2018 - Area 2 Final Capping Activities

June 2018 - Absorbent Boom Replacement

June 2018 - Absorbent Boom Replacement

June 2018 - Paving Over Temporary Utility Trench in South Parking Lot

June 2018 - Paving Over Temporary Utility Trench in South Parking Lot

June 2018 - Summer Covering of Stockpile

June 2018 - Summer Covering of Stockpile

June 2018 - Telecommunication Installation for Pier Building

June 2018 - Telecommunication Installation for Pier Building

June 2018 - Stockpile Liner Installation

June 2018 - Stockpile Liner Installation

June 2018 - Installing construction fabric and crushed stone over finished ISS area

June 2018 - Installing construction fabric and crushed stone over finished ISS area

June 2018 - Grading crushed stone over construction fabric in finished ISS area

June 2018 - Grading crushed stone over construction fabric in finished ISS area

June 2018 - Installing construction fabric over finished ISS area in preparation for installing crushed stone.

June 2018 - Installing construction fabric over finished ISS area in preparation for installing crushed stone.

June 2018 - Stockpile management

June 2018 - Stockpile management

June 2018 - Temporary sewer line installation in South Parking Lot

June 2018 - Temporary sewer line installation in South Parking Lot

June 2018 - Installing construction fabric and crushed stone over finished ISS area

June 2018 - Installing construction fabric and crushed stone over finished ISS area

June 2018 - Decommissioning grout plant silos

June 2018 - Decommissioning grout plant silos

June 2018 - Relocating Grout Plant Silos for Staging

June 2018 - Relocating Grout Plant Silos for Staging

June 2018 - Temporary Sewer Line Installation in South Parking Lot

June 2018 - Temporary Sewer Line Installation in South Parking Lot

June 2018 - Installing construction fabric and crushed stone over finished ISS area

June 2018 - Installing construction fabric and crushed stone over finished ISS area

June 2018 - Re-Covering Stockpile with Poly Sheeting

June 2018 - Re-Covering Stockpile with Poly Sheeting

May 2018 - Absorbent Boom Replacement in River

May 2018 - Absorbent Boom Replacement in River

May 2018 - End of the Day Posi-Shell Application on Stockpile

May 2018 - End of the Day Posi-Shell Application on Stockpile

May 2018 - Temporary Sewer Line Install in South Parking Lot

May 2018 - Temporary Sewer Line Install in South Parking Lot

May 2018 - Managing Overburden Stockpile

May 2018 - Managing Overburden Stockpile

May 2018 - Applying Posi-Shell with Concrete for Weekend

May 2018 - Applying Posi-Shell with Concrete for Weekend

May 2018 - Installing Replacement Tie-Rod Close to Bulkhead

May 2018 - Installing Replacement Tie-Rod Close to Bulkhead

May 2018 - Temporary Sewer Line Installation in South Parking Lot

May 2018 - Temporary Sewer Line Installation in South Parking Lot

May 2018 - Testing 'Odor Boss' with ISS in Main Quanta Area

May 2018 - Testing 'Odor Boss' with ISS in Main Quanta Area

May 2018 - Severance Area Clean-Up

May 2018 - Severance Area Clean-Up

May 2018 - ISS on Main Quanta Site

May 2018 - ISS on Main Quanta Site

May 2018 - End of the Day Posi-Shell Application

May 2018 - End of the Day Posi-Shell Application

May 2018 - Exposing Tie-Rods and Applying Rusmar Foam

May 2018 - Exposing Tie-Rods and Applying Rusmar Foam

May 2018 - Installing Plastic Sheeting on Soil Stockpile

May 2018 - Installing Plastic Sheeting on Soil Stockpile

May 2018 - South Parking Lot Clean-Up Activities

May 2018 - South Parking Lot Clean-Up Activities

May 2018 - End of the Day Posi-Shell Application

May 2018 - End of the Day Posi-Shell Application

May 2018 - Exposing Tie-Rods for Upgrades

May 2018 - Exposing Tie-Rods for Upgrades

April 2018 - Re-Covering Soil Stockpile

April 2018 - Re-Covering Soil Stockpile

April 2018 - Trenching for Temporary Electric in South Parking Lot

April 2018 - Trenching for Temporary Electric in South Parking Lot

April 2018 - Backfilling and ISS on the Main Quanta Site

April 2018 - Backfilling and ISS on the Main Quanta Site

April 2018 - Trailer Complex Relocation

April 2018 - Trailer Complex Relocation

April 2018 - Temporary electric installation in South Parking Lot

April 2018 - Temporary electric installation in South Parking Lot

April 2018 - Infiltration sump installation on main Quanta site

April 2018 - Infiltration sump installation on main Quanta site

April 2018 - Absorbent boom replacement

April 2018 - Absorbent boom replacement

April 2018 - ISS on the main Quanta site

April 2018 - ISS on the main Quanta site

April 2018 - ISS on the main Quanta site

April 2018 - ISS on the main Quanta site

April 2018 - Installing construction fabric and crushed stone over finished ISS area

April 2018 - Installing construction fabric and crushed stone over finished ISS area

April 2018 - Installing construction fabric and crushed stone over finished ISS area

April 2018 - Installing construction fabric and crushed stone over finished ISS area

April 2018 - Backfilling behind the sheet pile

April 2018 - Backfilling behind the sheet pile

April 2018 - Installing construction fabric and crushed stone over finished ISS area

April 2018 - Installing construction fabric and crushed stone over finished ISS area

April 2018 - Trenching for temporary electric in south parking lot

April 2018 - Trenching for temporary electric in south parking lot

April 2018 - Loading treated wood into roll-off and foaming

April 2018 - Loading treated wood into roll-off and foaming

April 2018 - Backfilling behind northeast corner of bulkhead

April 2018 - Backfilling behind northeast corner of bulkhead

March 2018 - Building new 'clean haul road' across site

March 2018 - Building new 'clean haul road' across site

March 2018 - Paving finished ISS area

March 2018 - Paving finished ISS area

March 2018 - Grading finished ISS area

March 2018 - Grading finished ISS area

March 2018 - Installing construction fabric and crushed stone over finished ISS area

March 2018 - Installing construction fabric and crushed stone over finished ISS area

March 2018 - Restoration North of the 115 River Road Building

March 2018 - Restoration North of the 115 River Road Building

March 2018 - Removal of an Underground Storage Tankin the South Parking Lot

March 2018 - Removal of an Underground Storage Tankin the South Parking Lot

March 2018 - Maintenance of the Decon Pad

March 2018 - Maintenance of the Decon Pad

March 2018 - Grading, with Poly Sheet Covering and Posi-Shell for Odor Control

March 2018 - Grading, with Poly Sheet Covering and Posi-Shell for Odor Control

March 2018 - Removing Berm Material from Completed ISS Area

March 2018 - Removing Berm Material from Completed ISS Area

March 2018 - Grading and Applying Posi-Shell in the Main Quanta Site

March 2018 - Grading and Applying Posi-Shell in the Main Quanta Site

March 2018 - Trenching for Temporary Electric in South Parking Lot

March 2018 - Trenching for Temporary Electric in South Parking Lot

February 2018 - Clearing and Applying Rusmar Foam in the Main Quanta Site

February 2018 - Clearing and Applying Rusmar Foam in the Main Quanta Site

February 2018 - ISS with Bucket Excavator in the Main Quanta Area

February 2018 - ISS with Bucket Excavator in the Main Quanta Area

February 2018 - Perimeter Misting System Operation

February 2018 - Perimeter Misting System Operation

February 2018 - Foaming with Rusmar During Clearing

February 2018 - Foaming with Rusmar During Clearing

February 2018 - Applying Posi-Shell at the End of the Day

February 2018 - Applying Posi-Shell at the End of the Day

February 2018 - Installing Poly at the End of the Work Week

February 2018 - Installing Poly at the End of the Work Week

February 2018 - Subsurface Concrete Removal on the Main Quanta Site

February 2018 - Subsurface Concrete Removal on the Main Quanta Site

February 2018 - Clearing on the Main Quanta Site for Concrete Removal

February 2018 - Clearing on the Main Quanta Site for Concrete Removal

February 2018 - Removing Backfill from Behind the Bulkhead

February 2018 - Removing Backfill from Behind the Bulkhead

February 2018 - Pre-Clearing, ISS, and Posi-Shell Application on the Main Quanta Site

February 2018 - Pre-Clearing, ISS, and Posi-Shell Application on the Main Quanta Site

February 2018 - Clearing on the Main Quanta Site

February 2018 - Clearing on the Main Quanta Site

February 2018 - Installing Plastic Covering on the Main Quanta Site

February 2018 - Installing Plastic Covering on the Main Quanta Site

February 2018 - Backfilling Behind Bulkhead

February 2018 - Backfilling Behind Bulkhead

February 2018 - Removing Wood Pilings from the Main Quanta Site

February 2018 - Removing Wood Pilings from the Main Quanta Site

February 2018 - BioSolve Application During ISS on the Main Quanta Site

February 2018 - BioSolve Application During ISS on the Main Quanta Site

January 2018 - Pre-Clearing and Posi-Shell Application on the Main Quanta Site

January 2018 - Pre-Clearing and Posi-Shell Application on the Main Quanta Site

January 2018 - Crushing Category 1 Stone

January 2018 - Crushing Category 1 Stone

January 2018 - ISS on the Main Quanta Site

January 2018 - ISS on the Main Quanta Site

January 2018 - Posi-Shell Application

January 2018 - Posi-Shell Application

January 2018 - Concrete Removal on the Main Quanta Site

January 2018 - Concrete Removal on the Main Quanta Site

January 2018 - Preparing Site for Relocated Crusher

January 2018 - Preparing Site for Relocated Crusher

January 2018 - Loading Roll-Off Boxes

January 2018 - Loading Roll-Off Boxes

January 2018 - Material Management on the Main Quanta Site

January 2018 - Material Management on the Main Quanta Site

January 2018 - Crushing Operations on the Main Quanta Site

January 2018 - Crushing Operations on the Main Quanta Site

January 2018 - Posi-Shell Application to Control Odors

January 2018 - Posi-Shell Application to Control Odors

January 2018 - ISS, Pre-Clearing, and Posi-Shell Application on the Main Quanta Site

January 2018 - ISS, Pre-Clearing, and Posi-Shell Application on the Main Quanta Site

January 2018 - Clearing on the Main Quanta Site

January 2018 - Clearing on the Main Quanta Site

January 2018 - Foam Application/Stockpile Management

January 2018 - Foam Application/Stockpile Management

January 2018 - Decon Pad Relocation

January 2018 - Decon Pad Relocation

January 2018 - Clearing and Obstruction Management on the Main Quanta Site

January 2018 - Clearing and Obstruction Management on the Main Quanta Site

January 2018 - Decon Pad Relocation

January 2018 - Decon Pad Relocation

December 2017 - Western Perimeter Fence Line Relocation

December 2017 - Western Perimeter Fence Line Relocation

December 2017 - Final Restoration South of 115 River Road

December 2017 - Final Restoration South of 115 River Road

December 2017 - Stockpile Management and Crushing Operations

December 2017 - Stockpile Management and Crushing Operations

December 2017 - Clearing and ISS on the Main Quanta Site

December 2017 - Clearing and ISS on the Main Quanta Site

December 2017 - South Parking Lot Clean-Up

December 2017 - South Parking Lot Clean-Up

December 2017 - Transporting Pilings from Clearing on Main Quanta Site

December 2017 - Transporting Pilings from Clearing on Main Quanta Site

December 2017 - Clearing and Foaming on the Main Quanta Site

December 2017 - Clearing and Foaming on the Main Quanta Site

December 2017 - iPark Paving

December 2017 - iPark Paving

December 2017 - Crushing Operations (with foam)

December 2017 - Crushing Operations (with foam)

December 2017 - Pier Building Water Line Installation

December 2017 - Pier Building Water Line Installation

November 2017 - Restoration South of 115 River Road

November 2017 - Restoration South of 115 River Road

November 2017 - Pier Building Water Line Installation

November 2017 - Pier Building Water Line Installation

November 2017 - Paving South of 115 River Road

November 2017 - Paving South of 115 River Road

November 2017 - Pier Building Water Line Installation

November 2017 - Pier Building Water Line Installation

November 2017 - Pre-Clearing on the Main Quanta Site

November 2017 - Pre-Clearing on the Main Quanta Site

November 2017 - ISS on the Main Quanta Site

November 2017 - ISS on the Main Quanta Site

November 2017 - Posi-Shell Application

November 2017 - Posi-Shell Application

November 2017 - Backfilling Activities

November 2017 - Backfilling Activities

October 2017 - ISS and Pre-Clearing

October 2017 - ISS and Pre-Clearing

October 2017 - Restoration and Concrete Removal

October 2017 - Restoration and Concrete Removal

October 2017 - Misting System

October 2017 - Misting System

October 2017 - Crane Staging Location

October 2017 - Crane Staging Location

October 2017 - Wharf Removal

October 2017 - Wharf Removal

October 2017 - Clearing Work

October 2017 - Clearing Work

October 2017 - ISS and Posi-Shell Application

October 2017 - ISS and Posi-Shell Application

October 2017 - Restoration

October 2017 - Restoration

September 2017 - PSE&G gas line work

September 2017 - PSE&G gas line work

September 2017 - Non-toxic foam applied to exposed soil to help control odors

September 2017 - Non-toxic foam applied to exposed soil to help control odors

September 2017 - Re-grading after completion of ISS

September 2017 - Re-grading after completion of ISS

September 2017 - Applying a durable, weather-proof, hard shell covering (posi-shell) to exposed soil to help control odors

September 2017 - Applying a durable, weather-proof, hard shell covering (posi-shell) to exposed soil to help control odors

September 2017 - Removing underground debris

September 2017 - Removing underground debris

September 2017 - Installation of a “clean road” (for construction vehicles that do not contact areas of contamination)

September 2017 - Installation of a “clean road” (for construction vehicles that do not contact areas of contamination)

September 2017 - Stockpile management

September 2017 - Stockpile management

August 2017 - Removing concrete

August 2017 - Removing concrete

August 2017 - Installation of steel sheetpile bulkhead outboard of main Quanta property

August 2017 - Installation of steel sheetpile bulkhead outboard of main Quanta property

August 2017 - Completion of walkway on the south side of 115 River Road for visitors to the Pier 115 restaurant

August 2017 - Completion of walkway on the south side of 115 River Road for visitors to the Pier 115 restaurant

July 2017 - Preparation of Block 93 for remediation

July 2017 - Preparation of Block 93 for remediation

July 2017 - ISS of soils on Block 93

July 2017 - ISS of soils on Block 93

July 2017 - Preparation of area south of 115 River Road Building for remediation

July 2017 - Preparation of area south of 115 River Road Building for remediation

July 2017 - Showing progress of the shoreline bulkhead installation

July 2017 - Showing progress of the shoreline bulkhead installation

July 2017 - Bracing installed on west wall of pier 115

July 2017 - Bracing installed on west wall of pier 115

July 2017 - Repairs and striping of parking lot on north side of 115 River Road building

July 2017 - Repairs and striping of parking lot on north side of 115 River Road building

July 2017 - Relocation of the batch plant to the east side of River Road

July 2017 - Relocation of the batch plant to the east side of River Road

July 2017 - Completion of access road from north to south of 115 River Road for parking

July 2017 - Completion of access road from north to south of 115 River Road for parking

July 2017 - Looking at excavators and batch plant on main Quanta property

July 2017 - Looking at excavators and batch plant on main Quanta property

July 2017 - Applying foam for odor suppression on the main Quanta

July 2017 - Applying foam for odor suppression on the main Quanta

July 2017 - Stockpile of soil

July 2017 - Stockpile of soil

July 2017 - ISS mixing activities on the main Quanta property

July 2017 - ISS mixing activities on the main Quanta property

July 2017 - Opening of access road from north to south of 115 River Road building

July 2017 - Opening of access road from north to south of 115 River Road building

July 2017 - Management of concrete on the main Quanta property

July 2017 - Management of concrete on the main Quanta property

July 2017 - Restoring portions of Block 93

July 2017 - Restoring portions of Block 93

July 2017 - Cutting off sheet piles to appropriate elevation outboard of main Quanta property

July 2017 - Cutting off sheet piles to appropriate elevation outboard of main Quanta property

July 2017 - Installation of steel sheetpile bulkhead outboard of main Quanta property

July 2017 - Installation of steel sheetpile bulkhead outboard of main Quanta property

July 2017 - ISS activities on the main Quanta property

July 2017 - ISS activities on the main Quanta property

July 2017 - Applying foam to remediation activities for odor suppression on main Quanta property

July 2017 - Applying foam to remediation activities for odor suppression on main Quanta property

July 2017 - Preparing area south of 115 River Road for remediation activities

July 2017 - Preparing area south of 115 River Road for remediation activities

July 2017 - Progress of steel sheetpile bulkhead

July 2017 - Progress of steel sheetpile bulkhead

June 2017 - Water quality controls during bulkhead work

June 2017 - Water quality controls during bulkhead work

June 2017 - Clearing vegetation east of River Road in preparation for ISS

June 2017 - Clearing vegetation east of River Road in preparation for ISS

June 2017 - Installing steel bulkhead to protect the river north of the 115 River Road pier

June 2017 - Installing steel bulkhead to protect the river north of the 115 River Road pier

June 2017 - Using a bucket auger to mix concrete and contaminated soils (ISS) west of River Road. Collecting ISS sample

June 2017 - Using a bucket auger to mix concrete and contaminated soils (ISS) west of River Road. Collecting ISS sample

June 2017 - Spraying foam to suppress odors around ISS site west of River Road

June 2017 - Spraying foam to suppress odors around ISS site west of River Road

June 2017 - Using a bucket auger to mix cement and contaminated soil (ISS) west of River Road

June 2017 - Using a bucket auger to mix cement and contaminated soil (ISS) west of River Road

June 2017 - Completed ISS west of River Road

June 2017 - Completed ISS west of River Road

June 2017 - Mixing cement and contaminated soil (ISS) west of River Road and using foam to suppress odors

June 2017 - Mixing cement and contaminated soil (ISS) west of River Road and using foam to suppress odors

May 2017 - Constructing a temporary parking lot for the pier building

May 2017 - Constructing a temporary parking lot for the pier building

May 2017 - Covering exposed soils west of River Road with foam to suppress odors

May 2017 - Covering exposed soils west of River Road with foam to suppress odors

March 2017 - Looking southeast toward the former 115 River Road building after demolition of the first 100-feet of building

March 2017 - Looking southeast toward the former 115 River Road building after demolition of the first 100-feet of building

March 2017 - Looking southeast toward active demolition of the 115 River Road building in preparation for the OU1 Remedial Action

March 2017 - Looking southeast toward active demolition of the 115 River Road building in preparation for the OU1 Remedial Action