Progress Photos

May 2019 - Erecting Area 3A Tent

May 2019 - Erecting Area 3A Tent

May 2019 - Trenching for Pier Building Gas Line Relocation

May 2019 - Trenching for Pier Building Gas Line Relocation

April 2019 - Erecting Area 3A Tent

April 2019 - Erecting Area 3A Tent

April 2019 - Laying Out Area 3A Tent

April 2019 - Laying Out Area 3A Tent

April 2019 - Bulkhead Brackets for Tent Support

April 2019 - Bulkhead Brackets for Tent Support

April 2019 - Tent Support Bracket Installation on Bulkhead

April 2019 - Tent Support Bracket Installation on Bulkhead

April 2019 - Assembling Crane

April 2019 - Assembling Crane

April 2019 - Offloading ISS Tent Delivery

April 2019 - Offloading ISS Tent Delivery

April 2019 - Dust Control Activities

April 2019 - Dust Control Activities

April 2019 - Area 7 Soil Stockpile Posi-Shell Application

April 2019 - Area 7 Soil Stockpile Posi-Shell Application

April 2019 - Grading Area 7 to Prepare for Tent Installation

April 2019 - Grading Area 7 to Prepare for Tent Installation

April 2019 - ISS Tent Generator Gas Line Installation

April 2019 - ISS Tent Generator Gas Line Installation

April 2019 - Erecting Grout Plant Silos

April 2019 - Erecting Grout Plant Silos

April 2019 - Offloading ISS Tent Air Handling Systems

April 2019 - Offloading ISS Tent Air Handling Systems

April 2019 - Grout Plant Water Line Installation

April 2019 - Grout Plant Water Line Installation

April 2019 - Installing ISS Tent Generator

April 2019 - Installing ISS Tent Generator

March 2019 - Demolition Material Management

March 2019 - Demolition Material Management

March 2019 - Compacting Ground Surface in Demo Area

March 2019 - Compacting Ground Surface in Demo Area

March 2019 - Area 3A Soil Stockpile Maintenance

March 2019 - Area 3A Soil Stockpile Maintenance

March 2019 - Demolition Material Management

March 2019 - Demolition Material Management

March 2019 - Trenching for ISS Tent Generator Gas Line and Electric

March 2019 - Trenching for ISS Tent Generator Gas Line and Electric

March 2019 - Preparing Transformer Pad for ISS Tent Electric

March 2019 - Preparing Transformer Pad for ISS Tent Electric

March 2019 - Swapping Absorbent Boom in Waterway

March 2019 - Swapping Absorbent Boom in Waterway

March 2019 - Hammering Above-Grade Building Foundation

March 2019 - Hammering Above-Grade Building Foundation

February 2019 - Segment A Bulkhead Installation

February 2019 - Segment A Bulkhead Installation

February 2019 - Segregating and Stockpiling Demolition Debris

February 2019 - Segregating and Stockpiling Demolition Debris

February 2019 - Sizing Steel for Offsite Disposal

February 2019 - Sizing Steel for Offsite Disposal

February 2019 - Loading Demolition Debris into Roll-Offs

February 2019 - Loading Demolition Debris into Roll-Offs

February 2019 - Segregating and Stockpiling Demolition Debris

February 2019 - Segregating and Stockpiling Demolition Debris

February 2019 - Backfilling Segment B Bulkhead

February 2019 - Backfilling Segment B Bulkhead

February 2019 - Cutting Segment B Sheets to Elevation

February 2019 - Cutting Segment B Sheets to Elevation

February 2019 - Pre-Trenching for Utilities for Bulkhead Installation

February 2019 - Pre-Trenching for Utilities for Bulkhead Installation

January 2019 - 115 River Road Demolition

January 2019 - 115 River Road Demolition

January 2019 - Re-Installing Pier Building Pedestrian Walkway

January 2019 - Re-Installing Pier Building Pedestrian Walkway

January 2019 - Segment A Bulkhead Installation

January 2019 - Segment A Bulkhead Installation

January 2019 - Securing Pier Building Driveway Road Plates in Place

January 2019 - Securing Pier Building Driveway Road Plates in Place

January 2019 - Swapping Absorbent Boom in Waterway

January 2019 - Swapping Absorbent Boom in Waterway

January 2019 - Auxiliary Parking Lot Parking Space Striping

January 2019 - Auxiliary Parking Lot Parking Space Striping

January 2019 - Demolition Material Management

January 2019 - Demolition Material Management

January 2019 - 115 River Road Demolition

January 2019 - 115 River Road Demolition

December 2018 - Preparing Auxiliary Parking Lot Area for Paving

December 2018 - Preparing Auxiliary Parking Lot Area for Paving

December 2018 - Above-Grade Building Foundation Removal

December 2018 - Above-Grade Building Foundation Removal

December 2018 - Demolition Material Management

December 2018 - Demolition Material Management

November 2018 - 115 River Road Exterior Demolition

November 2018 - 115 River Road Exterior Demolition

November 2018 - 115 River Road Exterior Demolition and Dust Control

November 2018 - 115 River Road Exterior Demolition and Dust Control

October 2018 - 115 River Road Interior Demolition

October 2018 - 115 River Road Interior Demolition

November 2018 - 115 River Road Interior Demolition

November 2018 - 115 River Road Interior Demolition

November 2018 - Demolition Debris Management

November 2018 - Demolition Debris Management

October 2018 - 115 River Road Exterior Demolition and Dust Control

October 2018 - 115 River Road Exterior Demolition and Dust Control

October 2018 - 115 River Road Demolition Material Management

October 2018 - 115 River Road Demolition Material Management

October 2018 - 115 River Road Interior Demolition

October 2018 - 115 River Road Interior Demolition

October 2018 - 115 River Road Exterior Demolition and Dust Control

October 2018 - 115 River Road Exterior Demolition and Dust Control

October 2018 - 115 River Road Interior Demolition

October 2018 - 115 River Road Interior Demolition

October 2018 - 115 River Road Exterior Demolition and Dust Control

October 2018 - 115 River Road Exterior Demolition and Dust Control

October 2018 - 115 River Road Interior Demolition

October 2018 - 115 River Road Interior Demolition

September 2018 - 115 River Road Gas and Electric Meter Removal

September 2018 - 115 River Road Gas and Electric Meter Removal

August 2018 - Demobilizing Loader from Main Quanta Site

August 2018 - Demobilizing Loader from Main Quanta Site

August 2018 - Area 7 Soil Stockpile Cover Maintenance

August 2018 - Area 7 Soil Stockpile Cover Maintenance

August 2018 - 115 River Road Clean-Up for Prepare for Demolition

August 2018 - 115 River Road Clean-Up for Prepare for Demolition

August 2018 - Preparing for ACM Abatement at 115 River Road

August 2018 - Preparing for ACM Abatement at 115 River Road

August 2018 - Parking Lot Striping at Area 2

August 2018 - Parking Lot Striping at Area 2

August 2018 - Universal Waste Removal in 115 River Road

August 2018 - Universal Waste Removal in 115 River Road

August 2018 - Deploying Rodent Traps for 115 RR Demolition

August 2018 - Deploying Rodent Traps for 115 RR Demolition

August 2018 - Area 2 Final Capping Activities

August 2018 - Area 2 Final Capping Activities

June 2018 - Absorbent Boom Replacement

June 2018 - Absorbent Boom Replacement

June 2018 - Paving Over Temporary Utility Trench in South Parking Lot

June 2018 - Paving Over Temporary Utility Trench in South Parking Lot

June 2018 - Summer Covering of Stockpile

June 2018 - Summer Covering of Stockpile

June 2018 - Telecommunication Installation for Pier Building

June 2018 - Telecommunication Installation for Pier Building

June 2018 - Stockpile Liner Installation

June 2018 - Stockpile Liner Installation

June 2018 - Installing construction fabric and crushed stone over finished ISS area

June 2018 - Installing construction fabric and crushed stone over finished ISS area

June 2018 - Grading crushed stone over construction fabric in finished ISS area

June 2018 - Grading crushed stone over construction fabric in finished ISS area

June 2018 - Installing construction fabric over finished ISS area in preparation for installing crushed stone.

June 2018 - Installing construction fabric over finished ISS area in preparation for installing crushed stone.

June 2018 - Stockpile management

June 2018 - Stockpile management

June 2018 - Temporary sewer line installation in South Parking Lot

June 2018 - Temporary sewer line installation in South Parking Lot

June 2018 - Installing construction fabric and crushed stone over finished ISS area

June 2018 - Installing construction fabric and crushed stone over finished ISS area

June 2018 - Decommissioning grout plant silos

June 2018 - Decommissioning grout plant silos

June 2018 - Relocating Grout Plant Silos for Staging

June 2018 - Relocating Grout Plant Silos for Staging

June 2018 - Temporary Sewer Line Installation in South Parking Lot

June 2018 - Temporary Sewer Line Installation in South Parking Lot

June 2018 - Installing construction fabric and crushed stone over finished ISS area

June 2018 - Installing construction fabric and crushed stone over finished ISS area

June 2018 - Re-Covering Stockpile with Poly Sheeting

June 2018 - Re-Covering Stockpile with Poly Sheeting

May 2018 - Absorbent Boom Replacement in River

May 2018 - Absorbent Boom Replacement in River

May 2018 - End of the Day Posi-Shell Application on Stockpile

May 2018 - End of the Day Posi-Shell Application on Stockpile

May 2018 - Temporary Sewer Line Install in South Parking Lot

May 2018 - Temporary Sewer Line Install in South Parking Lot

May 2018 - Managing Overburden Stockpile

May 2018 - Managing Overburden Stockpile

May 2018 - Applying Posi-Shell with Concrete for Weekend

May 2018 - Applying Posi-Shell with Concrete for Weekend

May 2018 - Installing Replacement Tie-Rod Close to Bulkhead

May 2018 - Installing Replacement Tie-Rod Close to Bulkhead

May 2018 - Temporary Sewer Line Installation in South Parking Lot

May 2018 - Temporary Sewer Line Installation in South Parking Lot

May 2018 - Testing 'Odor Boss' with ISS in Main Quanta Area

May 2018 - Testing 'Odor Boss' with ISS in Main Quanta Area

May 2018 - Severance Area Clean-Up

May 2018 - Severance Area Clean-Up

May 2018 - ISS on Main Quanta Site

May 2018 - ISS on Main Quanta Site

May 2018 - End of the Day Posi-Shell Application

May 2018 - End of the Day Posi-Shell Application

May 2018 - Exposing Tie-Rods and Applying Rusmar Foam

May 2018 - Exposing Tie-Rods and Applying Rusmar Foam

May 2018 - Installing Plastic Sheeting on Soil Stockpile

May 2018 - Installing Plastic Sheeting on Soil Stockpile

May 2018 - South Parking Lot Clean-Up Activities

May 2018 - South Parking Lot Clean-Up Activities

May 2018 - End of the Day Posi-Shell Application

May 2018 - End of the Day Posi-Shell Application

May 2018 - Exposing Tie-Rods for Upgrades

May 2018 - Exposing Tie-Rods for Upgrades

April 2018 - Re-Covering Soil Stockpile

April 2018 - Re-Covering Soil Stockpile

April 2018 - Trenching for Temporary Electric in South Parking Lot

April 2018 - Trenching for Temporary Electric in South Parking Lot

April 2018 - Backfilling and ISS on the Main Quanta Site

April 2018 - Backfilling and ISS on the Main Quanta Site

April 2018 - Trailer Complex Relocation

April 2018 - Trailer Complex Relocation

April 2018 - Temporary electric installation in South Parking Lot

April 2018 - Temporary electric installation in South Parking Lot

April 2018 - Infiltration sump installation on main Quanta site

April 2018 - Infiltration sump installation on main Quanta site

April 2018 - Absorbent boom replacement

April 2018 - Absorbent boom replacement

April 2018 - ISS on the main Quanta site

April 2018 - ISS on the main Quanta site

April 2018 - ISS on the main Quanta site

April 2018 - ISS on the main Quanta site

April 2018 - Installing construction fabric and crushed stone over finished ISS area

April 2018 - Installing construction fabric and crushed stone over finished ISS area

April 2018 - Installing construction fabric and crushed stone over finished ISS area

April 2018 - Installing construction fabric and crushed stone over finished ISS area

April 2018 - Backfilling behind the sheet pile

April 2018 - Backfilling behind the sheet pile

April 2018 - Installing construction fabric and crushed stone over finished ISS area

April 2018 - Installing construction fabric and crushed stone over finished ISS area

April 2018 - Trenching for temporary electric in south parking lot

April 2018 - Trenching for temporary electric in south parking lot

April 2018 - Loading treated wood into roll-off and foaming

April 2018 - Loading treated wood into roll-off and foaming

April 2018 - Backfilling behind northeast corner of bulkhead

April 2018 - Backfilling behind northeast corner of bulkhead

March 2018 - Building new 'clean haul road' across site

March 2018 - Building new 'clean haul road' across site

March 2018 - Paving finished ISS area

March 2018 - Paving finished ISS area

March 2018 - Grading finished ISS area

March 2018 - Grading finished ISS area

March 2018 - Installing construction fabric and crushed stone over finished ISS area

March 2018 - Installing construction fabric and crushed stone over finished ISS area

March 2018 - Restoration North of the 115 River Road Building

March 2018 - Restoration North of the 115 River Road Building

March 2018 - Removal of an Underground Storage Tankin the South Parking Lot

March 2018 - Removal of an Underground Storage Tankin the South Parking Lot

March 2018 - Maintenance of the Decon Pad

March 2018 - Maintenance of the Decon Pad

March 2018 - Grading, with Poly Sheet Covering and Posi-Shell for Odor Control

March 2018 - Grading, with Poly Sheet Covering and Posi-Shell for Odor Control

March 2018 - Removing Berm Material from Completed ISS Area

March 2018 - Removing Berm Material from Completed ISS Area

March 2018 - Grading and Applying Posi-Shell in the Main Quanta Site

March 2018 - Grading and Applying Posi-Shell in the Main Quanta Site

March 2018 - Trenching for Temporary Electric in South Parking Lot

March 2018 - Trenching for Temporary Electric in South Parking Lot

February 2018 - Clearing and Applying Rusmar Foam in the Main Quanta Site

February 2018 - Clearing and Applying Rusmar Foam in the Main Quanta Site

February 2018 - ISS with Bucket Excavator in the Main Quanta Area

February 2018 - ISS with Bucket Excavator in the Main Quanta Area

February 2018 - Perimeter Misting System Operation

February 2018 - Perimeter Misting System Operation

February 2018 - Foaming with Rusmar During Clearing

February 2018 - Foaming with Rusmar During Clearing

February 2018 - Applying Posi-Shell at the End of the Day

February 2018 - Applying Posi-Shell at the End of the Day

February 2018 - Installing Poly at the End of the Work Week

February 2018 - Installing Poly at the End of the Work Week

February 2018 - Subsurface Concrete Removal on the Main Quanta Site

February 2018 - Subsurface Concrete Removal on the Main Quanta Site

February 2018 - Clearing on the Main Quanta Site for Concrete Removal

February 2018 - Clearing on the Main Quanta Site for Concrete Removal

February 2018 - Removing Backfill from Behind the Bulkhead

February 2018 - Removing Backfill from Behind the Bulkhead

February 2018 - Pre-Clearing, ISS, and Posi-Shell Application on the Main Quanta Site

February 2018 - Pre-Clearing, ISS, and Posi-Shell Application on the Main Quanta Site

February 2018 - Clearing on the Main Quanta Site

February 2018 - Clearing on the Main Quanta Site

February 2018 - Installing Plastic Covering on the Main Quanta Site

February 2018 - Installing Plastic Covering on the Main Quanta Site

February 2018 - Backfilling Behind Bulkhead

February 2018 - Backfilling Behind Bulkhead

February 2018 - Removing Wood Pilings from the Main Quanta Site

February 2018 - Removing Wood Pilings from the Main Quanta Site

February 2018 - BioSolve Application During ISS on the Main Quanta Site

February 2018 - BioSolve Application During ISS on the Main Quanta Site

January 2018 - Pre-Clearing and Posi-Shell Application on the Main Quanta Site

January 2018 - Pre-Clearing and Posi-Shell Application on the Main Quanta Site

January 2018 - Crushing Category 1 Stone

January 2018 - Crushing Category 1 Stone

January 2018 - ISS on the Main Quanta Site

January 2018 - ISS on the Main Quanta Site

January 2018 - Posi-Shell Application

January 2018 - Posi-Shell Application

January 2018 - Concrete Removal on the Main Quanta Site

January 2018 - Concrete Removal on the Main Quanta Site

January 2018 - Preparing Site for Relocated Crusher

January 2018 - Preparing Site for Relocated Crusher

January 2018 - Loading Roll-Off Boxes

January 2018 - Loading Roll-Off Boxes

January 2018 - Material Management on the Main Quanta Site

January 2018 - Material Management on the Main Quanta Site

January 2018 - Crushing Operations on the Main Quanta Site

January 2018 - Crushing Operations on the Main Quanta Site

January 2018 - Posi-Shell Application to Control Odors

January 2018 - Posi-Shell Application to Control Odors

January 2018 - ISS, Pre-Clearing, and Posi-Shell Application on the Main Quanta Site

January 2018 - ISS, Pre-Clearing, and Posi-Shell Application on the Main Quanta Site

January 2018 - Clearing on the Main Quanta Site

January 2018 - Clearing on the Main Quanta Site

January 2018 - Foam Application/Stockpile Management

January 2018 - Foam Application/Stockpile Management

January 2018 - Decon Pad Relocation

January 2018 - Decon Pad Relocation

January 2018 - Clearing and Obstruction Management on the Main Quanta Site

January 2018 - Clearing and Obstruction Management on the Main Quanta Site

January 2018 - Decon Pad Relocation

January 2018 - Decon Pad Relocation

December 2017 - Western Perimeter Fence Line Relocation

December 2017 - Western Perimeter Fence Line Relocation

December 2017 - Final Restoration South of 115 River Road

December 2017 - Final Restoration South of 115 River Road

December 2017 - Stockpile Management and Crushing Operations

December 2017 - Stockpile Management and Crushing Operations

December 2017 - Clearing and ISS on the Main Quanta Site

December 2017 - Clearing and ISS on the Main Quanta Site

December 2017 - South Parking Lot Clean-Up

December 2017 - South Parking Lot Clean-Up

December 2017 - Transporting Pilings from Clearing on Main Quanta Site

December 2017 - Transporting Pilings from Clearing on Main Quanta Site

December 2017 - Clearing and Foaming on the Main Quanta Site

December 2017 - Clearing and Foaming on the Main Quanta Site

December 2017 - iPark Paving

December 2017 - iPark Paving

December 2017 - Crushing Operations (with foam)

December 2017 - Crushing Operations (with foam)

December 2017 - Pier Building Water Line Installation

December 2017 - Pier Building Water Line Installation

November 2017 - Restoration South of 115 River Road

November 2017 - Restoration South of 115 River Road

November 2017 - Pier Building Water Line Installation

November 2017 - Pier Building Water Line Installation

November 2017 - Paving South of 115 River Road

November 2017 - Paving South of 115 River Road

November 2017 - Pier Building Water Line Installation

November 2017 - Pier Building Water Line Installation

November 2017 - Pre-Clearing on the Main Quanta Site

November 2017 - Pre-Clearing on the Main Quanta Site

November 2017 - ISS on the Main Quanta Site

November 2017 - ISS on the Main Quanta Site

November 2017 - Posi-Shell Application

November 2017 - Posi-Shell Application

November 2017 - Backfilling Activities

November 2017 - Backfilling Activities

October 2017 - ISS and Pre-Clearing

October 2017 - ISS and Pre-Clearing

October 2017 - Restoration and Concrete Removal

October 2017 - Restoration and Concrete Removal

October 2017 - Misting System

October 2017 - Misting System

October 2017 - Crane Staging Location

October 2017 - Crane Staging Location

October 2017 - Wharf Removal

October 2017 - Wharf Removal

October 2017 - Clearing Work

October 2017 - Clearing Work

October 2017 - ISS and Posi-Shell Application

October 2017 - ISS and Posi-Shell Application

October 2017 - Restoration

October 2017 - Restoration

September 2017 - PSE&G gas line work

September 2017 - PSE&G gas line work

September 2017 - Non-toxic foam applied to exposed soil to help control odors

September 2017 - Non-toxic foam applied to exposed soil to help control odors

September 2017 - Re-grading after completion of ISS

September 2017 - Re-grading after completion of ISS

September 2017 - Applying a durable, weather-proof, hard shell covering (posi-shell) to exposed soil to help control odors

September 2017 - Applying a durable, weather-proof, hard shell covering (posi-shell) to exposed soil to help control odors

September 2017 - Removing underground debris

September 2017 - Removing underground debris

September 2017 - Installation of a “clean road” (for construction vehicles that do not contact areas of contamination)

September 2017 - Installation of a “clean road” (for construction vehicles that do not contact areas of contamination)

September 2017 - Stockpile management

September 2017 - Stockpile management

August 2017 - Removing concrete

August 2017 - Removing concrete

August 2017 - Installation of steel sheetpile bulkhead outboard of main Quanta property

August 2017 - Installation of steel sheetpile bulkhead outboard of main Quanta property

August 2017 - Completion of walkway on the south side of 115 River Road for visitors to the Pier 115 restaurant

August 2017 - Completion of walkway on the south side of 115 River Road for visitors to the Pier 115 restaurant

July 2017 - Preparation of Block 93 for remediation

July 2017 - Preparation of Block 93 for remediation

July 2017 - ISS of soils on Block 93

July 2017 - ISS of soils on Block 93

July 2017 - Preparation of area south of 115 River Road Building for remediation

July 2017 - Preparation of area south of 115 River Road Building for remediation

July 2017 - Showing progress of the shoreline bulkhead installation

July 2017 - Showing progress of the shoreline bulkhead installation

July 2017 - Bracing installed on west wall of pier 115

July 2017 - Bracing installed on west wall of pier 115

July 2017 - Repairs and striping of parking lot on north side of 115 River Road building

July 2017 - Repairs and striping of parking lot on north side of 115 River Road building

July 2017 - Relocation of the batch plant to the east side of River Road

July 2017 - Relocation of the batch plant to the east side of River Road

July 2017 - Completion of access road from north to south of 115 River Road for parking

July 2017 - Completion of access road from north to south of 115 River Road for parking

July 2017 - Looking at excavators and batch plant on main Quanta property

July 2017 - Looking at excavators and batch plant on main Quanta property

July 2017 - Applying foam for odor suppression on the main Quanta

July 2017 - Applying foam for odor suppression on the main Quanta

July 2017 - Stockpile of soil

July 2017 - Stockpile of soil

July 2017 - ISS mixing activities on the main Quanta property

July 2017 - ISS mixing activities on the main Quanta property

July 2017 - Opening of access road from north to south of 115 River Road building

July 2017 - Opening of access road from north to south of 115 River Road building

July 2017 - Management of concrete on the main Quanta property

July 2017 - Management of concrete on the main Quanta property

July 2017 - Restoring portions of Block 93

July 2017 - Restoring portions of Block 93

July 2017 - Cutting off sheet piles to appropriate elevation outboard of main Quanta property

July 2017 - Cutting off sheet piles to appropriate elevation outboard of main Quanta property

July 2017 - Installation of steel sheetpile bulkhead outboard of main Quanta property

July 2017 - Installation of steel sheetpile bulkhead outboard of main Quanta property

July 2017 - ISS activities on the main Quanta property

July 2017 - ISS activities on the main Quanta property

July 2017 - Applying foam to remediation activities for odor suppression on main Quanta property

July 2017 - Applying foam to remediation activities for odor suppression on main Quanta property

July 2017 - Preparing area south of 115 River Road for remediation activities

July 2017 - Preparing area south of 115 River Road for remediation activities

July 2017 - Progress of steel sheetpile bulkhead

July 2017 - Progress of steel sheetpile bulkhead

June 2017 - Water quality controls during bulkhead work

June 2017 - Water quality controls during bulkhead work

June 2017 - Clearing vegetation east of River Road in preparation for ISS

June 2017 - Clearing vegetation east of River Road in preparation for ISS

June 2017 - Installing steel bulkhead to protect the river north of the 115 River Road pier

June 2017 - Installing steel bulkhead to protect the river north of the 115 River Road pier

June 2017 - Using a bucket auger to mix concrete and contaminated soils (ISS) west of River Road. Collecting ISS sample

June 2017 - Using a bucket auger to mix concrete and contaminated soils (ISS) west of River Road. Collecting ISS sample

June 2017 - Spraying foam to suppress odors around ISS site west of River Road

June 2017 - Spraying foam to suppress odors around ISS site west of River Road

June 2017 - Using a bucket auger to mix cement and contaminated soil (ISS) west of River Road

June 2017 - Using a bucket auger to mix cement and contaminated soil (ISS) west of River Road

June 2017 - Completed ISS west of River Road

June 2017 - Completed ISS west of River Road

June 2017 - Mixing cement and contaminated soil (ISS) west of River Road and using foam to suppress odors

June 2017 - Mixing cement and contaminated soil (ISS) west of River Road and using foam to suppress odors

May 2017 - Constructing a temporary parking lot for the pier building

May 2017 - Constructing a temporary parking lot for the pier building

May 2017 - Covering exposed soils west of River Road with foam to suppress odors

May 2017 - Covering exposed soils west of River Road with foam to suppress odors

March 2017 - Looking southeast toward the former 115 River Road building after demolition of the first 100-feet of building

March 2017 - Looking southeast toward the former 115 River Road building after demolition of the first 100-feet of building

March 2017 - Looking southeast toward active demolition of the 115 River Road building in preparation for the OU1 Remedial Action

March 2017 - Looking southeast toward active demolition of the 115 River Road building in preparation for the OU1 Remedial Action